Stormwater interceptor Project

Stormwater interceptor Project
0Comments

Mayor Victoria Woodards, City Manager Elizabeth Pauli, and Environmental Services Director Mike Slevin attended a ribbon-cutting event on March 18, 2022, for the “Thea Christiansen” tunneling machine. The machine will be used as part of the City of Tacoma’s Jefferson and Hood Street Surface Water Interceptor project to improve existing stormwater capacity, reduce urban flooding events downtown, and support future growth. 

 “This project is part of our continuing efforts to protect our businesses, museums, university, and all of downtown from local urbanized flooding caused by climate change which we have been experiencing over the last decade,” said Director Mike Slevin.

 Construction of the 60-inch diameter interceptor and new outfall into the Thea Foss Waterway began in fall 2021 and will take approximately one year to complete. The new outfall is designed to support stormwater drainage of more than 90,000 gallons per minute.

 “This is quite a complex project within our urban setting,” said Project Manager Christa Lee. “The project alignment runs through the heart of our city and has technically challenging site conditions.  Due to the need to cross a few significant transportation corridors, we selected the micro-tunneling method.”  

 The project includes both “open cut” construction and trenchless micro-tunneling methods, which will allow roadways to remain open during some portions of the work. The tunneling machine has launched its first of three tunnel drives the week of March 21, 2022.

 For more information on the City’s stormwater project, visit cityoftacoma.org/jeffersonhood or call (253) 279-5509. 

Original source can be found here.



Related

Grace Graham, Deputy Commissioner for Policy, Legislation, and International Affairs of FDA

FDA inspects World Import, Corp. facility in Sumner on March 3

World Import, Corp. in Sumner underwent an FDA inspection for foodborne biological hazards on March 3, as listed in official data from the FDA’s website.

Dr. Mehmet Oz CMS Administrator

Tacoma Medicaid spending on alcohol and drug abuse treatment reaches $18.6 million in 2024

Medicaid payments for Alcohol and Drug Abuse Treatment services in Tacoma rose 24.2% in 2024, highlighting a shift in healthcare utilization and reimbursement trends.

Dr. Mehmet Oz CMS Administrator

Gig Harbor Medicaid dental spending climbs to $344,503 in 2024

In 2024, Medicaid providers in Gig Harbor billed $344,503 for Dental Services, reflecting a 0.5% increase over the prior year.

Trending

The Weekly Newsletter

Sign-up for the Weekly Newsletter from Pierce Today.